Ship-to-Ship Loading of 10,900 Tons of Palm Kernel Shells in Pontianak Loading...
Read MoreLoading thousands of tons of cargo onto a ship is a complex operation that requires much more than simply moving cargo from one vessel to another. It involves close coordination between the vessel, cargo owner, surveyors, port authorities, barge operators, and local maritime teams.

A recent example took place at Pontianak, Indonesia, where MV Apollo Hina loaded 10,900 metric tons of Palm Kernel Shells (PKS) for transportation to Nakagusuku, Japan through a ship-to-ship cargo operation. TMA Group supported the vessel's port and cargo activities, helping coordinate the loading process, documentation, clearance, and departure.
The operation also highlights the importance of local maritime expertise and logistics coordination, particularly when weather conditions can affect vessel movements, cargo handling, and the timing of ship-to-ship operations.
MV Apollo Hina loaded 10,900.001 metric tons of Palm Kernel Shells (PKS) at Pontianak. Palm Kernel Shells are a by-product of palm oil production and can be used as biomass fuel, making them a commercially traded cargo in international supply chains.

The cargo was shipped from Pontianak, Indonesia, to Nakagusuku, Japan. Unlike a typical operation where cargo is loaded directly from a shore-based terminal, the PKS was transferred to MV Apollo Hina from barges while the vessel was at anchorage.
In simple terms, the journey was: Pontianak → Barge-to-Vessel Cargo Loading → Sea Voyage → Nakagusuku, Japan.
Ship-to-ship loading is the transfer of cargo directly from one vessel to another without the cargo first being discharged at a land-based terminal.

In this operation, the cargo was carried by barges and transferred directly into MV Apollo Hina's cargo holds. The barge came alongside the larger vessel, was secured safely, and cargo-handling equipment was used to move the Palm Kernel Shells from the barge into the ship.
A ship-to-ship operation may be used when:
Although the cargo transfer takes place between vessels, the operation still requires many of the same controls as a conventional loading operation. These include vessel preparation, cargo hold inspections, draft surveys, weather monitoring, safe mooring, cargo documentation, communication between crews, and coordination with authorities and surveyors.
Ship-to-ship loading also requires careful attention to the movement of both vessels. Wind, waves, current, visibility, barge readiness, and the condition of the mooring arrangements can all affect whether cargo operations can continue safely.
A barge is a type of flat-bottomed vessel commonly used to transport cargo over relatively short distances, particularly around ports, rivers, and coastal areas.
For MV Apollo Hina, the cargo was brought alongside the vessel using barges. The cargo was then transferred directly from each barge into the ship's cargo holds. This was therefore a barge-to-vessel ship-to-ship loading operation.
The operation depended not only on MV Apollo Hina being ready, but also on the availability, readiness, and safe positioning of each barge.
Three barges were involved during the loading operation:
Each barge brought cargo to MV Apollo Hina and was handled as part of the overall ship-to-ship loading sequence.
MV Apollo Hina completed its sea passage and arrived at Pontianak Anchorage at 01:42 on 14 August 2026.
An anchorage is an area where ships can safely wait or remain anchored before proceeding with other port activities. The vessel dropped anchor after arrival, but cargo operations could not begin immediately because of bad weather, which affected activities from 01:42 until 08:25.

Once conditions allowed operations to proceed, port authorities and TMA Group's agent boarded the vessel at 08:25, and Free Pratique was granted at 09:10, allowing the vessel to proceed with the necessary port activities.
Because the cargo was to be loaded ship-to-ship, the vessel also needed to remain safely positioned at anchorage while waiting for the barges to come alongside.
Before cargo could be loaded, several preparations had to take place.
The ship's crew spent time preparing the equipment and setting up the pontoon required for the operation. The pontoon and associated equipment supported the safe transfer of cargo between the barge and MV Apollo Hina.
The shipper and surveyors then boarded at 12:20 for a coordination meeting. This meeting helped align the vessel, cargo, survey, and operational teams before the first barge came alongside.
Two important surveys were also part of the process. The first was a draft survey, which estimates the amount of cargo on a ship by measuring changes in the vessel's draft, or how deeply the ship sits in the water.
A hold inspection was also carried out to check the condition of the spaces where the cargo would be placed. These checks help ensure that the vessel and its cargo spaces are ready before ship-to-ship loading begins.
At 15:10, the first cargo barge, BG. HP 230 No. 1, came alongside MV Apollo Hina.

Coming alongside means positioning the barge next to the receiving vessel and securing it so that cargo can be transferred safely. During a ship-to-ship operation, the crews must monitor the relative movement of both vessels and maintain safe mooring arrangements throughout the transfer.
After the barge was positioned, the crew prepared the equipment needed to transfer the cargo from the barge into MV Apollo Hina's cargo holds.
Loading began at 16:15 and continued until 01:00 on 15 August, when the first barge completed its operation.
Bad weather then interrupted activities from 01:00 to 03:40. Once conditions affected the safety or efficiency of the transfer, the operation had to be paused. The first barge subsequently left the vessel, and the operation waited for the next barge to become ready.
The second barge, BG. BB 11, arrived alongside MV Apollo Hina at 15:22 on 15 August. After the necessary equipment was prepared, loading resumed at 16:30, with the cargo transferred from the barge into the vessel's cargo holds. The operation continued through the night and into the following day.

BG. BB 11 completed its loading operation at 13:35 on 16 August and then left the vessel. However, the total cargo quantity had not yet been loaded, so MV Apollo Hina had to wait for the third barge to become available.
Cargo loading was suspended from 16 August until 19 August while the operation waited for the next barge to be ready. This delay shows how barge-to-vessel loading depends on the availability and coordination of several assets, not only the receiving vessel.

The third barge, BG. Newton Power 3001, arrived alongside MV Apollo Hina at 04:25 on 19 August. After the equipment was prepared, loading resumed at 06:15 and continued for more than a day as the remaining cargo was transferred into the vessel's holds.
Loading continued through 20 August, with an intermediate draft survey conducted between 17:00 and 18:00 before operations resumed. This survey helped monitor the quantity loaded and compare the vessel's condition with the cargo records.

The cargo loading was completed at 23:10 on 20 August, followed by a final draft survey completed at 01:00 on 21 August. The independent surveyors recorded a total cargo quantity of 10,900.001 MT, which was also entered on the vessel's Bill of Lading.
After the cargo quantity was confirmed, the cargo documentation was completed at 01:15 on 21 August. The vessel then underwent fumigation from 01:20 to 03:20 to control pests and other organisms in accordance with the cargo, destination, or applicable regulations.
The cargo holds were closed at 03:30 after fumigation was completed. The third barge left the vessel at 05:20, completing the barge-to-vessel cargo transfer phase.
Before MV Apollo Hina could leave Indonesia, the required departure procedures had to be completed. The shipper obtained customs clearance at 08:38, followed by port clearance at 10:30, confirming that the necessary regulatory and documentation requirements had been satisfied.
Once clearance was obtained, MV Apollo Hina raised anchor at 11:00 and departed Pontianak for Nakagusuku, Japan. The vessel was expected to arrive at its destination on 29 August 2026 at 15:00.

The MV Apollo Hina operation demonstrates how external factors can affect cargo transportation, particularly when cargo is transferred between vessels.
The vessel arrived at Pontianak on 14 August, but bad weather immediately delayed the start of operations.
Weather conditions can affect ship-to-ship loading in several ways:
Later, cargo loading also had to pause while the operation waited for the next barge to become ready.
This is one of the realities of maritime and logistics operations. Even when a vessel, cargo, equipment, and personnel are ready, operations can still be affected by weather, equipment availability, port conditions, barge readiness, and coordination between different parties.
Effective local coordination helps identify these challenges and manage the operation as efficiently and safely as possible.
| Details | Information |
|---|---|
| Vessel | MV Apollo Hina |
| Voyage | V-605 |
| Flag | Philippines |
| Loading Port | Pontianak, Indonesia |
| Discharge Port | Nakagusuku, Japan |
| Cargo | Palm Kernel Shells (PKS) |
| Cargo Loading Method | Ship-to-ship, barge-to-vessel |
| Arrival | 14 August 2026 |
| Loading Completed | 20 August 2026 |
| Departure | 21 August 2026 |
| Next Port | Nakagusuku, Japan |
| Barge Support | 3 Barges |
The MV Apollo Hina operation demonstrates that international cargo transportation involves a complex chain of activities, from vessel arrival and cargo preparation to barge coordination, cargo transfer, surveys, fumigation, documentation, customs clearance, and departure. Each stage must be carefully coordinated to keep the operation safe and efficient.
For bulk cargo and barge-to-vessel loading, local knowledge is particularly important. Understanding port and anchorage conditions, coordinating with authorities and service providers, monitoring weather, and maintaining communication between the vessel and cargo stakeholders can help keep operations moving.
TMA Group provides shipping agency, maritime, port, and logistics services across Indonesia, supporting vessel owners, operators, charterers, shippers, and cargo interests with local coordination and operational assistance. Whether a vessel is arriving, loading or discharging cargo, conducting a ship-to-ship transfer, or preparing for its next voyage, effective coordination helps connect every part of the maritime logistics chain.

From vessel arrival and port operations to cargo loading, barge coordination, and departure, effective local coordination helps keep vessels moving and cargo flowing.
TMA Group — supporting vessels and cargo across Indonesia.
Ship-to-Ship Loading of 10,900 Tons of Palm Kernel Shells in Pontianak Loading...
Read MoreHow a Cargo Ship Delivers 15,200 Tons of Potash to Gresik, Indonesia...
Read MoreTruck and Vessel Load Limits:Why Every Cargo Has a Maximum Capacity Do...
Read MoreDiscover the latest news, achievements, and industry updates from TMA Group.
Stay informed about how we continue to innovate and grow in the maritime industry.

Harbour Nine Business District Block C-12 Jl. Gresik, Surabaya - Jawa Timur
© 2026 All Rights Reserved.